– Fairly priced.

Auction products.

Bid on Prisma for our current storage products.

Haidach SY 22/23+23/24

Haidach SY 22/23+23/24

Storage location

Haidach (market area THE)

Allocation date

26/08/2021, 11:00–11:30 CET

Contract period

01/04/2022–01/04/2024

Allocation mode/Pricing

Key procedure/Pay-as-bid

Plattform

PRISMA

Capacity on offer

2000 GWh

Structure firm*

117 / 128 [days]

Structure interr.**

88 / 88 [days]

view more

Bundle structure

 

Volume firm

Volume interr.

Injection firm

Injection interr.

Withdrawal firm

Withdrawal interr.

01/04/2022

20,000,0000 kWh

6,500 kWh/h

3,000 kWh/h

7,100 kWh/h

2,400 kWh/h

01/04/2023

20,000,0000 kWh

6,500 kWh/h

3,000 kWh/h

7,100 kWh/h

2,400 kWh/h

Price model

Storage feeFixed price
Variable injection fee

0 €/MWh

Variable withdrawal fee

0 €/MWh

Service fee

0 €

  

Technical limitations

Renomination lead time delivery point 1

2 h

Renomination lead time delivery point 2

2 h

Technical lead times

Min flow
Miscallaneous

Transport / Delivery Points

 

Name

TSO

Market Area

Point-ID entry/exit

Offered Transport Capacity

Delivery point 1

USP Haidach

bayernets GmbH

THE

BAY-700069-8021-1/
BAY-700069-8021-2

FZK, bFZKtemp, DZK, UBK 

Delivery point 2

Speicher Haiming 3-Haidach

Open Grid Europe GmbH

THE

3433P/3433I

bFZKtemp, UBK

Injection Curve

IR [%] = WGV [%] x (–2) + 240

Withdrawal Curve

WR [%] = WGV [%] x 1.3333 + 60

Miscallaneous / Comments

No curve applies to interruptible capacity.

Free of charge usage of capacity between curve and nominal capacity on best effort basis (until further notice).

Capacity fully allocated.

open PRISMA Capacity Platform

Additional capacities and services

Additional capacities

There is more for you. Short-term capacities from within-day to all year round. 

view more

Remit

Time is money. We take over your storage status report to the authorities.  

view more

*min. time to fully inject/withdraw using firm rates without consideration of storage curves 
** min. time to fully inject/withdraw using firm and interruptible rates without consideration of storage curves